1.Over the work period of March 8- March 21, give a description of the work conducted by your team and the progress made on your project.
- Over the work period of March 8 – March 21 the team has started validation testing on the pressure tank by doing pressure cycling. The team has constructed 90% of the storage crate and has also started the process of acquiring the fishing equipment that will be used for other portions of the validation.
2. For the same work period, discuss any challenges or obstacles (technical or non-technical) that your team has faced. Follow up by explaining the solution implemented or your plan to address the challenge.
- The team has not encountered any challenges or obstacles within the time period. The team is slightly behind schedule but does not anticipate any major drawbacks that will cause them to not deliver a functioning device on time.
3. Describe the current status of your Team’s Validation Plan implementation. If possible, provide some preliminary results and explain how the results relate to a project goal or design expectation.
- Currently the team is testing the tank by pressure cycling it. The team has completed 25 cycles without seeing any mechanical failures, the goal is to complete 50 cycles to ensure that the tank will not experience any failures that could potentially yield the device unsafe for use or that may harm the user. The team has also validated the size component of the device and its storage create (with them being about 4 feet in length and 2 feet in width) by testing to sees if it will fit into different vehicle types.
4. Give at least 3 figures that are representative of the current status of your project. Explain these figures and their importance to your work.
- The figures below depict the current status of the project. Figures 1 & 2 show the storage crate that was constructed to hold the device and the pump. Figures 3 & 4 show the tank being filled with a compressor to conduct the pressure cycling section of the team’s validation plan.